Work- and Machine center load
In this article
The available capacity of a work- or machine center is defined by its calendar. Against this calendar, task are planned. The load expresses the difference between planning and calendar.
When planning a machine 6 hours against 8 hours on calendar, the load is 75%. Standard NAV shows this load in a separate form, by time period (day, week, month, quarter or year).
This Manufacturing Accelerator functionality provides a view in a matrix form, the y-axis being the work- or machine center, the x-axis the time period. The cells show the load percentage in a notification color:
Load < 80% | Blue |
Load between 80% and 120% | Green |
Load >120% | Red |
Setup
No setup is required for this functionality.
Execution
- Choose the icon, enter Capacity.On the Capacities Page, click Work Centers.
- From the Ribbon, select Calendar.
- The Work Center Calendar Filter Card appears.
- Select the View by (Month, Day,…) you wish to display.
- From the Ribbon, select Show Matrix.
- The Work Center Calendar Matrix appears.
- Verify the matrix when the Show option is put to Capacity
- Verify the matrix when the Show option is put to Planning
- Verify the matrix when the Show option is put to Work load It related to allocated time for production order
- Note that three extra filters can be applied:
With Planning Coefficient | No Subcontractors( only for Work Centers) | Only Bottlenecks |
IF Not checked:Value = "Capacity (Effective)" IF checked : Value = ROUND("Capacity (Effective)" * Planning / 100, 0.01) | Work/Machine Centers that are marked as Subcontractor will not be included. | Only Work/Machine Centers that are indicated as Bottleneck (Setting on the Work/Machine Card) will be included. |
Verify the matrix when the Show option is put to efficiency