Work- and Machine center load

In this article

Setup

Execution

See also

The available capacity of a work- or machine center is defined by its calendar. Against this calendar, task are planned. The load expresses the difference between planning and calendar.

When planning a machine 6 hours against 8 hours on calendar, the load is 75%. Standard NAV shows this load in a separate form, by time period (day, week, month, quarter or year).

This Manufacturing Accelerator functionality provides a view in a matrix form, the y-axis being the work- or machine center, the x-axis the time period. The cells show the load percentage in a notification color:

Load < 80% Blue
Load between 80% and 120% Green
Load >120% Red

Setup

No setup is required for this functionality.

Execution

  1. Choose the search icon, enter Capacity.On the Capacities Page, click Work Centers.
  2. From the Ribbon, select Calendar.
  3. The Work Center Calendar Filter Card appears.
  4. Select the View by (Month, Day,…) you wish to display.
  5. From the Ribbon, select Show Matrix.
  6. The Work Center Calendar Matrix appears.
  7. Verify the matrix when the Show option is put to Capacity
  8. Verify the matrix when the Show option is put to Planning
  9. Verify the matrix when the Show option is put to Work load It related to allocated time for production order
  10. Note that three extra filters can be applied:
With Planning Coefficient No Subcontractors( only for Work Centers) Only Bottlenecks
IF Not checked:Value = "Capacity (Effective)" IF checked : Value = ROUND("Capacity (Effective)" * Planning / 100, 0.01) Work/Machine Centers that are marked as Subcontractor will not be included. Only Work/Machine Centers that are indicated as Bottleneck (Setting on the Work/Machine Card) will be included.

Verify the matrix when the Show option is put to efficiency

See also

Set Up Work Centers and Machine Centers