PRODUCTION COMPONENTS AVAILABILITY

In this article

Setup

Execution

The Production Components Availability functionality shows the Replenishment Status of each Production component.

Setup

No setup is required for this functionality.

Execution

  1. Choose the search icon, enter Released Production Orders.
  2. From the List of Production Orders, select one and click View (or Edit) in the Ribbon.
  3. On the Lines Fast Tab, select the Assist Button Lines and click Components.
  4. The Production Components Page appears.

    Possible values for the Replenishment Status:

    Inventory The item can be taken from inventory
    Requisition Requisition line created for the purchase
    Purchase Item is purchased
    Plannend Planning Worksheet created
    Production Item is planned for production
    Other Item can be replenished by some other, check order tracking
    None Item is not planned on hand, action needs to be taken

Remarks:

  • When item is reserved, a "(r)" is added after the text:Inventory(r), means reserved from stock.
  • When multiple sources are tracked, the ",..." text is added, Planned,... means some quantities are planned, others have another source.
  • When there is a shortage, None is added: Purchase,...,None means some quantities are purchase, others have another source and some item are not available.
  • When there is a shortage (None in the text), the component line is marked (bold or an icon in front)
  • For items that are not set up to use Order Tracking the Replenishment Status will be set to No Information Available